How a Mine Closure (Liquidation) Plan Is Prepared

A liquidation plan sets out how a subsoil user will decommission the mine and other facilities, reclaim disturbed land and what this will cost. For the extraction of solid minerals in Kazakhstan, it is a mandatory document: the Subsoil Code prohibits mining where reclamation is not covered by a plan with positive expert review conclusions. Plans for liquidating the consequences of subsoil use differ by type of operation; this article deals with solid mineral mining areas.

When a plan is needed

Initial development of a liquidation plan for solid mineral mining is required before operations begin. The document is often prepared alongside the Mining Plan (PGR), as closure measures rely on the same facilities, outlines and schedule.

The second situation is an update. The Code requires the plan, together with the cost estimate, to be revised no later than three years after the latest positive expert review conclusions, and whenever the mining plan is amended on the grounds set out in Article 216(5): changes to the types and methods of extraction, volumes, timing, or the composition of production facilities and infrastructure. Revising the liquidation plan in these cases is not a formality: as operations change, so do the scope of closure measures and the amount of financial security.

The liquidation plan is the basis for the project that governs the closure works. Under Article 218(2) of the Subsoil Code, the subsoil user must ensure that the project is prepared, agreed with the relevant parties, subjected to expert review and approved no later than two years before the licence expires.

What the document contains

Its structure is set by the Instruction on Drawing up a Liquidation Plan, approved by Order No. 386 of the Minister for Investments and Development of the Republic of Kazakhstan dated 24 May 2018. The core section is organised by site facilities: underground workings, open pits, waste dumps, tailings storage facilities, buildings and equipment, roads, waste disposal sites and water management systems. For each of them, the plan describes:

  • current condition, risks and uncertainties;
  • decommissioning and reclamation measures;
  • closure objectives and criteria — measurable indicators used to verify that the outcome has been achieved;
  • post-closure monitoring and maintenance;
  • the approximate cost of the measures.

The document also covers the baseline environment, progressive reclamation, the schedule and financial security for closure obligations. A care-and-maintenance section is included where a temporary suspension of operations is planned.

Cost of the document versus cost of closure

These two figures are easily confused. The cost of developing the plan is the designer's fee; it depends on the complexity of the site, the completeness of input data and the scope of support. The approximate closure cost is an estimate of the closure measures themselves: demolition, regrading, revegetation, water treatment and monitoring. The methodology builds it from direct costs by facility and indirect costs — engineering, mobilisation, contractor overheads and contingencies — on the assumption that the work will be carried out by a third-party contractor. This figure determines the amount of financial security for closure obligations, including in the form of a bank guarantee or a pledge of a bank deposit.

Input data

The minimum data set is agreed with the designer. It typically includes:

  • site information: licence, boundaries, land documents and infrastructure;
  • mining data: the mining plan, schedule, and outlines of pits, waste dumps and tailings facilities;
  • environmental data: industrial environmental monitoring results, groundwater and surface water quality, and the environmental impact assessment;
  • the previous liquidation plan and expert review conclusions, where available.

How the work is carried out

Work starts with a review of the materials and, where necessary, a site visit. Objectives, criteria and measures are then defined for each facility, post-closure land use is agreed with the subsoil user, and the approximate cost is calculated. The Instruction requires stakeholder views to be taken into account: the findings are shared with stakeholders before the document is submitted for expert review.

The plan is prepared with the involvement of a party licensed to perform environmental protection work and services, and it is approved by the subsoil user. It then undergoes an industrial safety review, followed by the state environmental review. Support during review, responses to comments and timelines are defined by the agreed contractual scope.

Examples of completed plans

Minerals Operating has prepared liquidation plans for mining at the Shubarkol (hard coal), Dalabay (gold and silver) and Ayat deposits.

Where to start

Before getting in touch, prepare the name of the deposit, the stage of work, and the mining plan or the previous version of the liquidation plan. These determine the scope of the task and the input data required. More on this service is available on the Ecology page.